2008-08-04 e - Carter Announces Partners in Technology
2008-08-04 d - Carter PAV Estimated Performance Numbers
2008-08-04 c - Carter PAV Nears Completion
2008-08-04 b - Carter Appoints New VP and Adds Staff
2008-08-04 a - Carter Photo Captions - AirVenture 2008
2007-04-13 b - Carter Announces Change to R&D Philosophy
2007-04-13 a - Carter Releases New PAV Designs
2007-01-11 - CarterGyro Achieves Amazing Vertical Take-offs
2006-03-31 - "Carter FutureFlight-I" to Take to the Air
2005-06-17 - The CarterCopter Breaks the μ-1 Barrier!
2004-05-14 - CarterCopter Experiences In Flight Fire
2004-04-04 d - U.S. Army Awards Carter Data Collection Contract
2004-04-04 c - Carter Receives NASA STTR Award for a Personal Air Vehicle Design
2004-04-04 b - Carter is Testing Landing Gear for Licensing
2004-04-04 a - The CarterCopter is Back in the Air!
2003-12-01 - Carter Unveils Firefighting Heliplane
2003-11-07 - Carter Announces DARPA Contract
2003-10-08 - Carter Puts
μ-1 Barrier Attempt on Hold
2003-10-06 -
CarterCopter Rebuilding Update
2003-05-16 - OSAC to Partner with
Carter to Restore the CCTD
2003-04-14 - Flight Tests Superb
- Unfortunate Ending
2002-12-03 - New High-Mu
Rotor Passes First Round of Testing
2002-09-02 - Oshkosh 2002
2002-07-19 -
CarterCopter Technology Demonstrator will be at Oshkosh
2002-06-12 - Dual
flight controls and automated rotor system
2002-03-30 -
CCTD Exceeds NASA Goal of MU 0.8
2002-02-16 - Flight Envelope Expands
to a Mu of 0.69
2002-01-17 - CarterCopters Receives Propeller Patents
2001-12-13 - New Flight Records Set
2001-11-21 - Flight-testing Status Update
2001-10-05 - Failure of Modified Propeller
Leads to Design Improvement
2001-08-10 - Spinner Bracket Failure
Causes Emergency Landing
2001-08-09 - Airventure 2001
2001-07-22 - Progress Continues: New
Records
2001-07-12 - Record Flights Limited
Only by On-board Fuel
2001-07-03 - Military-Style Program
Pays Dividends: Additional 11 ½ Days of Progress
2001-05-30 - Persistence Leads to Breakthrough:
New Takeoff and Landing Procedures Developed
2001-03-28 - Incident Occurs During
Weekend Testing
2001-03-02 - Additional Test Pilots
Sign on with CarterCopters
2000-12-21 - Good News - Bad News
2000-11-20 - CarterCopter Achieves Its
First Zero Roll Take-Off
2000-10-26 - CarterCopter Resuming Flight
Testing
2000-07-13 - CarterCopter Re-assembly
and Final Testing
2000-06-12 - Repair, improvements &
component testing nearing completion
2000-02-24 - Status of repairs and improvements
1999-12-23 - Accident (Too much collective)
1999-11-23 - 6 days of flying
1999-10-11 - Corvette LS1 engine installation
1999-08-23 - More V6 engine problems
1999-06-11 - 1st flight pattern, unloaded
rotor 50%, engine problem
1999-05-17 - 3 delays
1999-04-05 - 2 days flying. No nose
extension. Best STOL to date.
1999-03-03 - Flight at Sheppard AFB.
3 Days. Low HP, failed muffler
1999-02-09 - Best flights to date, 2
hrs. flying, new control
1999-01-28 - New control, rotor blade
weave during ground tests
1998-11-18 - 13 runway passes. Problem
with hydraulic controls - Final straw
1998-11-04 - 1st flight after accident.
Rotor blade dogleg eliminated. Stick forces OK.
1998-09-24 - 1st flights, then accident
1998-08-25 - 1st taxi tests, prop counter
weight arm came off
1998-08-14 - Aircraft mechanically &
electrically complete
1998-06-03 - Aircraft painted &
mechanically complete
|